Kazakhstan
Construction and Operation of Street Lighting Networks in Atyrau (148.5 km) under the Batys Transit JSC Project
₸4,6bn
Project amount
Project overview
The project "Construction and Operation of Street Lighting Networks in the City of Atyrau" with a total length of 148,525 m is the fourth phase of JSC Batys Transit's programme for the construction of street lighting networks in the city of Atyrau. The project uses the public-private partnership mechanism and envisages the introduction of an Automated Outdoor Lighting Management System with dimming capability.
Project goals and objectives
Goal 1
Goal 2
Goal 3
Goal 4
Goal 5
Development impact
₸4.6bn
total project costs
5ths
poles installed
5ths
LED luminaires installed
75control cabinets
installed
0.4kV
170,000 metres of overhead line installation
10kV
5,000 metres of cable line installation
20substations
installed